Deep Pipelines for Aquaculture
Makai has designed for the State of Hawaii a larger warm
and cold-water intake system for supplying both cold and warm water for
aquaculture and ocean energy systems. Makai had full responsibility for the
pipelines and pump station from the survey through to the final design plans and
specifications. Estimated construction cost of the seawater supply system is 13
million dollars.
 |
|
Profile of
the 55” diameter polyethylene deep-water intake pipeline
(click to enlarge)
|
|
The 55” seawater supply system is a dual ocean intake.
One pipeline takes in seawater from a depth of 80’ and supplies over 50,000
gpm on shore. A second pipeline, approximately 10,000’ long and extending to a
depth of 3000’ brings in 27,000 gpm of seawater at 4 deg C. Each pipeline is
55” OD and primarily consists of polyethylene pipe.
The deep-water pipeline profile
is illustrated above. The offshore region had been surveyed extensively with
sidescan sonar that showed that the slopes were both steep and very rugged. The
sidescan data on the steep and highly reflective slopes in Hawaii was inadequate
for the detail required in a pipeline design. Makai surveyed the seabed with a
high-resolution acoustic bottom roughness survey system to determine roughness
resolution as fine as 6 inches. By knowing the capabilities, limitations, and
costs of various polyethylene pipeline approaches (see the design approaches
discussed below covering bottom, catenary, and pendant pipelines), a acceptable
route and design approach could be joined. The resultant design was a pipeline
that lies primarily on the seafloor, missing known obstacles. In the region of
500’ to 1600’ depth, the seabed is quite rough with old lava flows and
ledges. The pipeline has been designed to be pulled tight over this region where
it can span above the rough seabed due to the concave nature of the bathymetry.
A series of pendants attached to the pipeline in this region help restrict
movement due to high currents. A final survey was conducted with a series of
submarine dives confirming the route and location of specific obstacles.
The deployment of the 55” pipeline is to be completed by
the controlled submergence process developed by Makai and used previously on
deep-water pipelines ranging in size from 12” to 40” (see sections 6.2, 6.3
and 6.4). The primary difference for this pipeline is that it will be installed
in one continuous section and will reach a depth of 3000 feet. By extrapolating
from the success of earlier pipeline deployments, this larger and longer
pipeline can be safely deployed to this greater depth.
The near-shore portion of this pipeline was particularly
challenging because of the strict environmental constraints limiting trenching
and the very extreme design waves (48 feet) and strong surface currents. Because
of the large diameter of the pipelines, any surface mounted pipe would
experience extreme inertial loads. Tunneling approaches were investigated: both
slant drilling and micro-tunneling. Slant drilling was not contractually
feasible, not being able to obtain a firm fixed bid from any contractor. A
micro-tunneling approach was used and the design completed. Twin tunnels cross
the shoreline from the pump station 500’ inshore to the breakout 500’
offshore at a depth of 80 feet. The tunnels are steel tubes with concrete
carrier pipes grouted in place. The construction of this portion of the pipeline
has been completed.
The warm water intake structure and the offshore cold water
pipe attaches to the tunnels at 80’ depth. The deep-water portion of the
pipeline is primarily gravity anchored with the exception of the immediate
shallow region that has additional screw anchors for added stability. The intake
structure likewise is stabilized with screw anchors.
The pump station is on shore, approximately 500’ back
from the shoreline. Two pumps for each pipeline provide for the full flow, a
third pump is installed for each pipe as a backup. The cost of installing large
sumps in the very porous soil at Keahole, Hawaii prompted the design approach
illustrated below. The large intake pipelines are located well below grade and
open into an inlet screen well that separates any debris from the incoming
seawater. From that point, the water flows to three individual wells, each with
a vertical turbine pump, accessible from the surface. Sinking these
pre-fabricated well structures in a flooded pit proved to be a more economical
approach than the conventional large sump structure.
At present, the design
is complete and the near-shore twin tunnels have been constructed. The remainder
of the pipeline has been funded and is scheduled for construction in 2000 –
2001.
The state of Hawaii is developing a Hawaii Ocean Science
and Technology (HOST) Park on the Island of Hawaii to provide land and resources
to developing companies in aquaculture and energy. The HOST park includes
seawater supplies, both warm and deep cold water. Makai was responsible for the
design of the offshore pipelines.
 |
|
Profile of
the 40” HOST deep-water intake pipeline
(click to enlarge) |
|
The intake cold-water pipeline was one of the most
formidable engineering and construction challenges for the HOST Park
development. The pipeline design called for a total flow of 50,350 lpm (13,300
gpm) of deep, cold water at 5 to 6 degrees Centigrade (39-43°F)
from a depth greater than 640 m (2100 ft). The pipeline was designed to
withstand a 100-year storm and have a lifetime of 10 years or greater.
Because the final use for the cold water is to be for aquaculture and OTEC
research, the pipeline materials contacting the flowing water must be inert.
The bathymetry at Keahole is ideal for a
down-the-slope deep-water intake pipeline. The bathymetric profile
and the pipeline installation is illustrated above. The desired intake depth of
640 m (2100 ft) is less than 1.6 m (1 mile) offshore. The shore elevation is
approximately 3 m (10 ft) with a basalt cliff at the shoreline. In the shallow
water are boulders with occasional bedrock outcroppings. At a depth of 15 m (50
ft), approximately 92 m (300 ft) offshore, to a depth of 61 m (200 ft), the
bottom is coral rubble with slopes up to 40 degrees. Between the depths of 61 m
(200 ft) and 152 m (500 ft) the bottom is smooth with sand and small pebbles. At
152 m (500 ft) the bottom slope abruptly increases along an old reef. The slope
becomes 40 degrees or more at greater depths and the bottom is covered with old
lava flows and occasional boulders 3 m (10 ft) or more in diameter. At the pipe
intake area, the bottom is lightly sediment covered and smooth at about a 25
degree slope.
Keahole Point, being the western most point of the island
of Hawaii, frequently has strong currents. The 100 year design currents are 2.9
m/s (9 ft/s) at the surface, 1.3 m/s (4.2 ft/s) at 152 m (500 ft) and .4 m/s
(1.3 ft/s) at 305 m (1000 ft) and below. In addition, the pipeline has been
designed for a 100 year storm wave at 14.5 m (47.5 ft) ft high at 18 seconds in
the open ocean. Extreme wave and current events have been combined to yield a
100 year maximum load expected on the pipeline. In the shallow water, the
pipeline loads are wave dominated and in the deep water they are current
dominated.
The pipeline profile illustrates the general design
approach used for this pipeline. The pumps are located in a sump 76 m (250 ft)
inshore of the shoreline. From the pump station to 92 m (300 ft) offshore, the
pipeline is buried. From a depth of illustration A1 21 m (70 ft) to a depth of
152 m (500 ft), a distance of 640 m (2100 ft), the pipeline is held just off the
bottom with concrete anchors clamped to the pipeline. Beyond 152 m (500 ft)
depth and reaching to the bottom anchor at 701 m (2300 ft) depth, a continuous
band of polyethylene pipeline, 1030 m (3377 ft) long, freely floats above the
bottom. This long, inverted catenary is held in place with two large gravity
anchors at either end, 36.3 t (40 tons) at the top in 152 m (500 ft) of water
and 18.1 t (20 tons) at 701 m (2300 ft).
Polyethylene had been selected as the pipeline material for
this project. Polyethylene has significant advantages for this pipeline in that
it is inert and will neither corrode nor contaminate the cold water.
Polyethylene links can be heat fused together to form a long continuous pipeline
with joints that are as strong as the pipe itself. With its excellent strength
and flexibility, deploying a polyethylene pipe is far easier then other
materials. Furthermore, the polyethylene is buoyant in water, a characteristic
that provides for a great deal of design flexibility and deployment ease.
The lower portion of the pipeline is an inverted catenary,
1030 m (3377 ft) long, which floats several hundred feet above the steep bottom.
This catenary design has been used to avoid contact with the rough and generally
unsurveyed bottom beyond 152 m (500 ft) depth. The buoyancy in the inverted
catenary is provided by the buoyancy of the polyethylene material plus, in the
shallow region of high currents, fishing floats attached to the pipe. Even with
this buoyancy, the pipeline sways in the strong currents at Keahole. Under 100
year current conditions, the center of the catenary will move nearly 152 m (500
ft) horizontally and 76 m (250 ft) vertically. Under moderate and strong current
conditions, there will be vortex shedding on the pipeline and the pipeline may
or may not resonate. Even if the pipeline does resonate, the cyclic fatigue
limitations of polyethylene material will not be exceeded.
At the top of the inverted catenary the pipelines moves
through the transition region to become a fixed anchored pipeline. The
transition is a critical area of the pipeline becauset it is loaded by two
dimensional bending, very high tension and torsion due to the buoyancy and
movement of the catenary. At 152 m (500 ft), the catenary loads are transferred
through a external pipe clamp to a mooring line attached to the upper 36.3 t (40
ton) anchor. Therefore the bending is taken by a relatively unloaded portion of
the pipeline.
The bottom anchored pipe stretches between the depths of
152 m (500 ft) and 21 m (70 ft); it is 640 m (2100 ft) long. Pipeline anchors,
with a wet weight of 3062 kg (6750 lbs), are clamped at varying intervals along
the pipeline. The anchors support the pipeline 0.75 diameters off the bottom in
order to minimize hydrodynamic loading and to clear small obstacles on the
bottom. The spacing between weights varies since the loading and anchor
requirements diminish in the deeper water. The installed pipeline in this region
has an in place weight varying from 205 kg/m (138 lbs/ft) at 152 meters (500 ft)
to 1235 kg/m (830 lbs/ft) at 21 m (70 ft). The very high weight per ft in the
shallower portion of this region was achieved by adding saddle weights to the
pipeline after it was placed on the bottom. The shallow portion of the pipeline
is buried. The buried pipe stretches from the 21 m (70 ft) depth point, 92 m
(300 ft) offshore, through the cliff shoreline and to the pump station, 76 m
(250 ft) onshore.
The
cold water pipe is a long suction intake delivering 50,346 lpm (13,300 gpm) to
the submerged pumps onshore. The pipeline operates at 345 kPa (5 psi) suction
total, 9.2 kPa (1.33 psi) is due to the static head from the high-density cold
water. Because the pipeline suction requirement diminishes along the pipeline,
the pipe wall thickness is staggered; the pipeline has a diameter to wall
thickness (SDR) of 21 near the pump station and an SDR of 32.5 near the intake.
The pump station is within the high surf zone and built entirely below grade.
The 8 submersible pumps are installed in a covered sump 7.3 m (24 ft) deep.
Three of the pumps feed the Natural Energy Laboratory of Hawaii and 5 feed the
HOST Park.

The 1 m (40") HOST cold water pipe was assembled and
deployed in July, 1987. Assembly of the pipeline took place at Kawaihae Harbor,
35.4 km (22 miles) north of the deployment site. The pipeline was fused
together, anchor weights attached, and the assembly floated air-filled in
the harbor at Kawaihae. Two separate tows were made to the site delivering first
the near-shore portion of the pipeline, over 915 m (3000 ft) long and then
finally the latter part of the catenary section, 610 m (2000 ft) long. At
Keahole, the pipeline was controllably submerged and placed on the bottom.
The first section of pipe deployed was the shore section
stretching from 21 m (70 ft) depth to the mid-catenary flange, a pipe
length of 1131 m (3709 ft). This pipeline, air-filled and floating on the
surface, was anchored at the shore end and connected to shore pumps. A large tug
on the offshore end pulled the pipeline into alignment. By pumping water into
the pipeline at the shore end, the pipeline was controllably submerged to the
bottom. The internal pressure in the pipeline was controlled to prevent pipe
collapse. By pulling strongly offshore, regulating the flow of water into the
pipe and monitoring the air pressure inside the pipe, the pipeline submergence
was always in static equilibrium and could be easily controlled. This
submergence of the weighted portion of the pipe was a primary consideration in
the design of the pipeline. There was a fine balance in the required offshore
pull, minimum bend radii in the pipeline, internal pressure on the pipeline,
external pressure on the pipeline, point loads on the pipeline due to anchor
weights and temperature of the pipeline. The design of the deployment technique
was an intricate part of the overall pipeline design.
Prior to submerging the near-shore portion of the pipe, the
transition anchor and transition attachments were connected to the floating
pipeline. The transition anchor was then lowered with the submerging pipeline.
Once the transition anchor was placed on the bottom, the deployment of the first
section was complete and the end of the first section, 366 m (1200 ft) down the
inverted catenary from the transition, remained on the surface.
The second and final section of pipe was then towed from
Kawaihae to Keahole and the two flanged pipe sections were bolted together on
the surface. A pig was pumped through the pipeline to purge it of air, the
intake end of the pipeline was attached to the lower anchor and this was lowered
to the bottom in approximately 701 m (2300 ft) of water.
Makai Ocean Engineering designed for the Natural Energy
Laboratory of Hawaii an 18" back-up pipeline to the 12" pipeline
Makai had designed and installed 6 years earlier.
This work was performed for the Research Corporation of the University of
Hawaii.
 |
|
Profile of
the 18" deep-water intake pipeline
(click to enlarge) |
|
This
pipeline was installed approximately 1 mile south of Keahole Point, Hawaii, the
location of the 40" and 12" inverse catenary design pipelines.
American Divers, Inc. of Honolulu and Makai Ocean Engineering completed the
deep-water deployment in October, 1988.
The main restricting design criteria for the 18"
pipeline was cost. The State's budget was limited for construction of this
pipeline plus the State wanted to demonstrate new cost savings techniques for
the installation of deep-water polyethylene pipes. Compounding this restriction,
considerably less was known about the bottom conditions along this pipeline
route as opposed to previously laid pipelines and the acceptable pipeline
corridor was quite narrow.
The above figure illustrates the overall pipeline
configuration and shows the primary difference between this pipeline and the
preceding inverse catenary design concepts. The very shallow portion of the
pipeline, from the shoreline to the depth of 70', is rock bolted directly the
hard bottom with a series of tubular steel supports that are highly versatile
and adaptable to the very irregular bottom. Beyond the 70' depth and out to 500'
depth, the pipeline traverses a fairly smooth but narrow corridor and is held in
place with concrete weights similar to earlier designs. Beyond 500' depth, the
design changes are most apparent. The buoyant polyethylene pipe rises above the
bottom but is moored with a series of pendants, approximately 40' long, that are
distributed along the pipeline down to the intake at 2100'.
There are several design, budgetary and deployment
advantages to the pendant supported pipeline configuration. The pipe is
supported well above the bottom and therefore an accurate survey for a smooth
pipe route is not required. Secondly, some of the disadvantages of the catenary
are eliminated: the handling of the large clump anchors at either end of the
catenary during deployment is eliminated and the complex transition between the
moving catenary and the stationary pipeline is not necessary. Among the
disadvantages of the pendant system is the large number of suspended weights
dangling during deployment and the pipeline is still somewhat affected by bottom
features. Because of the considerable previous experience in handling and laying
polyethylene pipelines, it was felt that the pendants could be safely handled
without fouling.
Included in the development of this pipeline concept were
low cost pipe attachments, not requiring heavy steel clamps as used in the past,
such that the pipeline could be pulled safely at high tensions. This high
tensile load is a requirement during deployment.
The full length of this 6000' long pipeline was laid on the
bottom using the controlled flooding and submerging techniques used in the past.
This pipeline, however, used this technique to a conservatively greater depth.
The pipeline was flooded from the shore end to the offshore end, and the bitter
end was lowered with a cable to the sea floor. The submerging and lowering of
the pipeline took less then 12 hours.
The polyethylene pipe portion of this pipeline was
assembled at the Natural Energy Laboratory just prior to the deployment. The
pipe was placed on rollers and launched into the ocean through a ramp at the
shoreline. As the pipeline was pulled into the sea, pendants, weights and
various pipeline components were attached to the pipe near the shoreline. The
total launch took approximately 12 hours. The ability to launch a pipeline in
this manner demonstrates that a harbor or protected shoreline is not necessary
for installing a CWP. Prior pipelines had used the harbor at Kawaihae for their
installation but parallel projects at Keahole made it advantageous to launch
this pipeline on site.
The
relationship between the State of Hawaii, American Divers, the contractor, and
Makai Ocean Engineering, the designer, was unique. American Divers was selected
to construct the pipeline early in the planning stage. During the design, Makai
worked closely with American Divers in order to design a pipeline that could
cost effectively be deployed by American Divers and still meet the operational
requirements of the State of Hawaii. American Divers worked directly for the
State on a time and materials basis and all parties acknowledged that there are
significant risks that are inherent with any marine construction, the contractor
would work to the best of his ability and the ultimate risk would be taken by
the State.
One major difficulty with the 18" pipeline route was
the location of rocks on either side of the pipe route at depths between 240'
and 600'. Currents at Keahole can be quite high and on the day of deployment
exceeded 1.3 knots at times. The restricted deployment budget did not allow
precise acoustic navigation techniques nor even surface electronic navigation.
The pipeline was precisely deployed utilizing shore ranges and restraining lines
moored to the bottom at key placement locations.
The pipeline was smoothly and efficiently installed in
October, 1988. The pipeline was inspected the following December proving that
the pipe alignment and pendant arrangement is as designed.
|